TRANSIT · 2026

Omnitrans, LED Interior Lighting Upgrades

Construction Management · CTO 05

Construction management and electrical construction-phase support for LED interior lighting upgrades at Omnitrans’ East Valley and West Valley facilities.

CM task order executed; completion pending

West Valley Bus Yard and Maintenance FacilityView gallery · 4
West Valley Bus Yard and Maintenance Facility
Client
Omnitrans
Contract
MNT24-47
Schedule
CM task order issued October 27, 2026; signed November 2, 2026
Status
CM task order executed; completion pending
Locations

East Valley — 1700 West Fifth Street, San Bernardino, CA 92411

West Valley — 4748 Arrow Highway, Montclair, CA 91763

Our role.

  • Construction management
  • Electrical construction-phase support
  • Lighting and controls submittal review
  • RFI responses
  • Field and outage coordination
  • Schedule and change review
  • Closeout and record-document support
Project period2026
Explore construction management ↗

Let’s bring it
all together.

Connect with our Glendale team to discuss your project and engineering needs.