Omnitrans, LED Interior Lighting Upgrades
Construction Management · CTO 05
Construction management and electrical construction-phase support for LED interior lighting upgrades at Omnitrans’ East Valley and West Valley facilities.
CM task order executed; completion pending
View gallery · 4 
- Client
- Omnitrans
- Contract
- MNT24-47
- Schedule
- CM task order issued October 27, 2026; signed November 2, 2026
- Status
- CM task order executed; completion pending
- Locations
East Valley — 1700 West Fifth Street, San Bernardino, CA 92411
West Valley — 4748 Arrow Highway, Montclair, CA 91763
Project overview.
Omnitrans’ interior lighting modernization replaces existing lighting, typically fluorescent, with LED fixtures and updated controls at its East Valley and West Valley facilities in San Bernardino and Montclair. S Y Lee’s construction management and electrical construction-phase scope supports implementation of the lighting design through contractor coordination, electrical RFI responses and submittal review for fixtures, retrofit kits and control-system compatibility.
The assignment includes installation-sequence and schedule review, periodic field observations, and coordination of occupied-area access and lighting outages, with payment and change-proposal review as requested by Omnitrans. Closeout support covers controls startup, acceptance-test documentation, owner training, punch-list follow-up, operation and maintenance records, and record drawings prepared from contractor-furnished redlines.
Our role.
- Construction management
- Electrical construction-phase support
- Lighting and controls submittal review
- RFI responses
- Field and outage coordination
- Schedule and change review
- Closeout and record-document support
Project gallery
4 imagesLet’s bring it
all together.
Connect with our Glendale team to discuss your project and engineering needs.